Case Study

SVC to Increase Reliability and Reduce Congestion over Multiple 500 kV Lines

SVC to Increase Reliability and Reduce Congestion over Multiple 500 kV Lines

Pages 2 Pages

SVC to Increase Reliability and Reduce Congestion over Multiple 500 kV Lines A very large Static Var Compensator (SVC) supplied by ABB was commissioned at the end of 2007 at Allegheny Power’s Black Oak substation near Rawlings, Maryland. The instal- lation enhances the reliability on Allegheny Power’s 500kV Hatfield-Black Oak-Bedington transmission line – one of the most heavily-loaded lines in the PJM (Pennsylvania, Jersey, Maryland) Inter