Case Study
Superfund Site Achieves US EPA Compliance, Cuts Project Time and Costs with Innovative SAMCO Groundwater Treatment Plant Design
Superfund Site Achieves US EPA Compliance, Cuts Project Time and Costs with Innovative SAMCO Groundwater Treatment Plant Design
Deliver scalable groundwater treatment plant (GWTP) design to reduce contaminants per compliance standards, including: Reduction of hexavalent chromium levels to < 17 ppb & Reduction of total chromium concentration to < 100 ppb - SAMCO developed and delivered scalable GWTP plans designed remove chrome contaminants resulting from metal working activity at the client’s Superfund site. The GWTP design proposed SAMCO’s signature skid-mounted modular design to reduce overall project execution time by 50% and cut project costs by 30%. Incorporating specialized ion exchange (IX) resins & combined on- and off-site regenerable IX processes.