Case Study

Steam Blowing MP Steam Header

Steam Blowing MP Steam Header

Visit our website for more Case Studies and Insights at: fourquest.com/case-studies fourquest.com/insights A major global oil and gas producer approached FourQuest Energy to perform steam blows on the MP Steam header in their Northern Alberta facility. Highlights: › 400m of 30” piping required steam blowing. › Significant steam flow required to clean the system meant multiple silencers would be required. › The use of multiple silencers was able to accommodate the steam flow once it reached rates over the calculated requirements. Steam Blowing MP Steam Header CASE STUDY The MP steam header consisted of 400m of 30” piping, which would require more than one silencer set up to accommodate the required steam flow rate. During our pre-engineering phase, it was ca