Case Study

Engineering Efficiencies Developed for Air Blowing

Engineering Efficiencies Developed for Air Blowing

Visit our website for more Case Studies and Insights at: fourquest.com/case-studies fourquest.com/insights A northern Alberta Oil Sands company required 1km of 24” BFW line to be cleaned using targeted air blows as part of the pre-commissioning process. Highlights: › Over $72,000 in immediate client savings were realized by our engineered set up and rig in process. › 1km of 24” BFW line was cleaned to a target specification by splitting the line into only 3 sections. Engineering Efficiencies Developed for Air Blowing CASE STUDY Due to the size of the line, the procedure was developed to split the line into three sections for the air blows. By dividing the line into three sections, we were able to execute the air blows with a single 1600cfm air compressor and d