Case Study
Stanlow Oil Refinery, Ellesmere Port
march 2013 stanlow oil refinery, ellesmere port case study temporary bridging mabey hire Conditions The replacement Cyclone head weighing 475 tonnes, delivered on a Mammoet special transport vehicle bringing the total vehicle weight to a massive 650 tonnes. Equipment Quickbridge Installation Extras Mat 125 Twin Joist supports Project Replacing the largest cyclone head in Europe at the Stanlow Main Contractors Hutchinson Engineering Ltd he Cyc