PROJECT PROFILE Summary Following unusually heavy rainfall, subsidence had become evident. The rail had subsided and deflected beyond safe tolerances during operation of the stacker-reclaimer. In 15 days Uretek Deep-Injection and Uretek Slab- Lifting had the rail re-levelled and fully re-supported. Objectives To re-level the stacker-reclaimer rail and to densify the sub-grade and re-support the affected portions of the rail and its concrete