Case Study
Shell UK NGL Plant Mossmorran
Shell UK NGL Plant Mossmorran Removal and disposal of Cristobalite debris which was discovered within the furnace (module 2 – DFSS01 during routine shut-down inspection, removal of debris was carried out under controlled “asbestos removal” conditions. Material was found on base of furnace which was approximately 4m2. Sureclean Scope Provide manpower and equipment to remove and dispose of the debris. Technical Challenge Restrictions / Considerations Timeline - Critical Path Project Project Management, resourcing, planning and scheduling Hazardous Environment - Confined Space Entry Working Waste containment and transfer Key Facts Project completed without safety or environmental incident. Project completed on time and within budget. Involved 3x Sureclean personnel, dayshift work over weeken