Case Study
Seneca High School
SENECA HIGH SCHOOL CASE STUDY 201 Spring Street, Peoria IL 61603 |www.ecsi-alc.com|Phone: (309) 683-5252|Fax: (309) 713-1800 QUICK GLIMPSE Customer Seneca High School Measures Implemented Control System Retrofit Total Project Cost $313,690.00 Estimated Annual Energy Savings 484,976 kWh 38,886 Therms Estimated Annual Cost Savings $69,714.65 /year DCEO Incentives Received $192,167.36 Estimated Payback 1.46 years OUR SOLUTION ECSI developed a plan to remove the existing BAS and install an award-winning BAS by Automated Logic ® that is a native BACnet ® (open protocol communications). The intuitive interface for this system is called WebCTRL ® . In addition to the installed hardware, ECSI installed new outside air temperature and humidity sensors, diffe