Case Study
Royal Albert basin
Contract in brief Location: Beckton, East London Client: London Development Agency Consulting Engineers: White Young Green Environmental HBR Role: Main Contractor Form of Contract: ICE Design and Building 2nd Edition Contract Value: £9.35M Contract Start: March 2005 Contract Period: 40 wks HBR site management Contracts Manager: Roger Lyes Project Manager: G Jones Contract Summary: The site comp