Case Study

Middlehaven Dock

Middlehaven Dock

Pages 1 Pages

Contract in brief Location: Middlesbrough Client: English Partnerships Consulting Engineers: White Young Green Design and Build Team: Babtie, Harbour and General, Blackwell Blackwell Role: Main Contractor Form of Contract: NEC Option A Contract Value: £3.2M (Full Scheme £12M) Contract Start: April 2000 Contract Period: 78 wks Blackwell site management Contracts Manager: T Barron Project Manager: