Case Study
Rosemount X-well optimizes heat exchanger efficiency— saves significant downtime and maintenance costs
Rosemount X-well optimizes heat exchanger efficiency— saves significant downtime and maintenance costs
“X-well Technology saves us an estimated $100,000 in annual operational costs” CHEMICAL Rosemount TM X-well TM optimizes heat exchanger efficiency— saves significant downtime and maintenance costs RESULTS • Improved operation efficiency by balancing parallel heat exchanger cooling loads • Reduce heat exchanger down time by providing real time information on heat exchanger performance • Predictive maintenance capability to avoid future damage, saving more than $100,000 annually APPLICATION A chemical plant using river water to provide cooling to ethylene oxide production. The flow rate of cooling water must be kept between a specific range to prevent future damage to heat exchangers. At velocities above the range, erosion occurs. At velocities below the range, Microbial Induced Cor