Reedbed Refurbishment – BSW Timber Yard

Reedbed Refurbishment – BSW Timber Yard

Reedbed Refurbishment – BSW Timber Yard Could this large, commercial reedbed be refurbished? A large timber company in Wales has had a reedbed treatment system in place for many years to treat the wastewater run-off from their yard including substantial amounts of sawdust and liquor from bark chippings. Reeds growing in refurbished reedbed Reedbed refurbishment Unfortunately, the reedbed had ceased to function effectively as wastewater was bypassing the inlet to the reedbed due to the accumulation of soil at the inlet area. The company was in danger of failing Environment Agency discharge checks so it was a matter of urgency that the reedbed system was refurbished. JPR re-engineered the inlet and divided the existing bed into two compartments which means half the reedbed can be rested at a