Case Study
Pure Gym
Case study Client: Pure Gym Location: Leicester Date: November 2015 Duration: 7 weeks Value: £646,000 Overview At their Leicester premises, Pure Gym was looking for a contractor to undertake the complete refurbishment of a 22,000 ft2 basement area that had previously been used as a hotel car park. The brief required the project to be completed in time for New Year trading so our team reworked the standard 10-week programme and provided around-the-clock services to ensure the challenging deadline was met. The existing concrete building was lined, with the walls and ceiling soffit receiving a white spayed decoration finish. Jumbo partition walls and suspended ceilings were installed to form the m