Case Study

Public High School

Public High School

Public High School Building Type: Public High School Project Type: Retrofit Qualifying Systems: Lighting/HVAC Square Footage: 302,473 Energy Savings: 35.80% LPD Reduction: 68.50% Deduction Per Square Foot: $1.20 Total Section 179D Deduction: $362,967.60 As part of a performance services contract with an energy services company (ESCO), an energy efficient retrofit was completed for an entire public school system. Highlighted in this case study is one of the high schools where the HVAC system was upgraded with building system controls and sensors and a T8 lighting upgrade was completed throughout the facility. The ESCO, as project designer, secured the allocation of the Section 179D tax deduction from the municipal owner and then engaged Concord’s services to complete the Section 179D certif

Join for free to read