Case Study
Productivity rises more than 20% in just 8 weeks for Multi-National
1 http:/ /pinnacle-strategies.com Productivity rises more than 20% in just 8 weeks for Multi-National Pinnacle Strategies delivers lightning fast results for global engineer to order manufacturing firm Huisman At their plant in Zhangzhou, China, heavy construction equipment manufacturer Huisman’s management team were facing a major problem. The company was in the process of building the world’s largest vessel-mounted crane: a seven-story high giant capable of lifting 10,000 tons. However, a series of delays meant there was some risk that the project would not be delivered on time. It was a situation that was becoming all too familiar. It seemed every project they undertook was plagued with a constant stream of holdups and last minute firefighting to deliver on time. Often, the pr