Case Study

Pontyclun: STOR

Pontyclun: STOR

Pages 2 Pages

CASE STUDY PONTYCLUN: STOR HEADLINES KEY FACTS 90% of prefabricated stainless steel pipework of steelwork pipe supports of the pipework fabricated off-site Project title: Pontyclun STOR Location: South Wales Value: £805,000 Duration: 20 weeks (8 weeks prefabricating, 12 weeks on-site installing) G&H divisions : F abrication 7 metre long, 1.2 metre wide combined flue stacks 1 MILE 8 TONNES 4x CASE STUDY HOW WE DID IT This large-scale scheme demonstrates our ability to manage the entire process, making best use of our fabrication facility, experienced workforce and extensive knowledge of STOR projects. The scheme was pre-designed by the client and we assembled a specialist team of engineers, welders, site supervisors and pro