Case Study
Option agreement “Securing the second storm flood protection line of the public flood protection of the city of Hamburg”
Option agreement “Securing the second storm flood protection line of the public flood protection of the city of Hamburg”
Option agreement “Securing the second storm flood protection line of the public flood protection of the city of Hamburg” Builder-owner/approving authority: State Office of Roads, Bridges and Waterways (LSBG) Protection goal: BW (7.30 m above sea level) + freeboard Load: in acc. with the guidelines for public flood protection in Hamburg Dimensions: 0.6 – 4.35 m, altogether approx. 1,000 m² of mobile space In the past, the city of Hamburg Ham-