Old Davidson's Mill Development, Multi Utility connections for 260 homes

Old Davidson's Mill Development, Multi Utility connections for 260 homes

Pages 2 Pages

Old Davidson's Mill Development, Multi Utility connections for 260 homes – Clancy Docwra Description: Laying of main water trunk and electrical spine to a master plan development of 1,500 units including commercial areas. Multi utility connections of 260 homes inside the first phases of the development. Challenges: Extremely tight window of operation because of traffic disruptions; no option to extend programme.Key achievements and innovations: Strong professional relationships with Scottish Water. We involved the provider in early decision-making through high level meetings; what normally takes months, took weeks in this case. Given the success of the initial water mains phase, Barratt awarded further work on the spine electrical infrastructure contract. After good performance on both fr