A Marmon Wire & Cable / Berkshire Hathaway Company Project NYSEG Substation 124 Turnkey Client RG&E/ Iberdrola USA Location Pennfield, NY Cable Design 138 kV, 2000 kcmil CU – High Voltage Cable Length 1,980 Circuit Feet Scope Observed cable pull through owner supplied duct bank, installation of 12 G&W PAT 140 terminations and cable shield ground equipment. Upon completion a final system acceptance 240kV DC Hi-POT test was conducted. Kerite