Case Study
Natural Gas Company Adds Rail Car Loading / Unloading Racks
Natural Gas Company Adds Rail Car Loading / Unloading Racks A large natural gas midstream transportation and processing company turns to MA VERICK for a solution to add rail car loading / unloading racks on a fast-tracked project. Objective The natural gas industry is experiencing a renaissance, one that requires quick responses to market conditions. A large midstream company relied on MAVERICK to provide controls system cause and effect diagrams, control panel design validation, system programming, factory testing, commissioning and overall project management of controls-related subcontractors to meet an aggressive project schedule. Results MAVERICK served as the main automation contractor (MAC), managing all parties and self-executing the project plan to completion. The proj