MTP, a private telecom infrastructure operator in Mexico, partnered with Vertiv to build a 2.7 MW data center in Santa Fe, Mexico City. The challenge was to maximize energy efficiency and meet Uptime Tier III standards within a compact 1,000-square-meter space. Vertiv delivered a tailored solution using its VR Racks, DCE Optimized Rack Systems, cold aisle containment, Liebert EXL S1 UPS, and Liebert DSE cooling systems. The result was a highly efficient, Tier III-certified data center with automated controls that reduced operational costs and enabled flexible interconnection—enhancing MTP's service offerings and competitiveness.