MOSES and SACS Simulations Help Dockwise Cut Topsides Float-over Time in Half

MOSES and SACS Simulations Help Dockwise Cut Topsides Float-over Time in Half

Pages 2 Pages

Dockwise Achieves Schedule for Transport and Installation of World’s Heaviest Topsides Using Bentley Technology Fast Facts • Dockwise was the T&I contractor selected to install the record- breaking jacket and topsides in terms of weight. • Bentley’ s offshore platform analysis, design, and installation software was selected for detailed design. • MicroStation and ProjectWise were used by team members in project offices located in The Netherlands, United States, and China. ROI • Efficiencies achieved during detail design saved 5,000 man-hours of the 30,000 engineering hours. • Simulations conducted using MOSES and SACS cut the estimated topsides float-over time from four days to two days.