Monks Abbey Primary School
/procuredirect @procuredirect Procure Direct Ltd 4 Poachers Lane, Sudbrooke, Lincoln LN2 2GA www.procuredirect.co.uk 01522 595858 info@procuredirect.co.uk CASE STUDY Monks Abbey Primary School The Brief We were asked to look at all areas of the school, with the aim of reducing energy consumption and improving light quality. It was requested that there be no disruption to school life, so ideally during school summer holidays. Key Targets: • Reduction of energy usage • Improvement of light quality • Payback of 5 years or less (for Salix Compliance) • No disruption to day to day running of the school The Solution In the classrooms and corridors the existing light fi ttings were either too old or not in the best possible location for maximum light. This enabled use of our New LED fi xed