Case Study
Molded Fiber Machine Installation Detail Design
Molded Fiber Machine Wenatchee, WA This project installed additional molded ber manufacturing capacity at the Keyes Packaging Wenatchee plant site to meet current and future demand for molded ber products. The project included installation of two new molded ber machines, which added 27 TPD of capacity to the plant. The Challenge: The plant had undergone a number of expansions over the years and physical space was limited for addition of two new molded ber machines. Additionally, the pulping and stock preparation systems were already operating at maximum production capacity. The Solution: Harris Group worked with the Owner to develop options for locations for installation of the new machine. The preferred option was to utilize existing warehouse space for manufacturing. A new warehous