Misterton Salt Barn

Misterton Salt Barn

Pages 3 Pages

MISTERTON SALT BARN Client: BAM NUTTALL LTD Commencement Date: August 2014 Programme: 10 Weeks Project Value: £771,672.00 Highways Agency Depot, Misterton Salt Barn, M1 Jct 20, Leicestershire Misterton Salt Barn The Misterton Salt Barn project, contracted to Storefield by BAM Nuttall, was a soil treatment and processing scheme to minimise the environmental impact of disposal of potentially contaminated soils to landfill. The project involved the processing of a stock pile of approximately 10,500m3 of mixed soils, demolition rumble, green waste and builders waste, which had been left at the highways agency site by the previous occupier. The table below shows the number of loads and weight of the different material types processed from the stockpi