Masonic Hall, Brightlingsea Before After The Project: Complete Reconstruction of the front elevation wall & porch of the Masonic Hall in Brightlingsea. Works comprised of new foundations, brickwork and groundwork. There were also mechanical & electrical and joinery works carried out within the porch area. Unusually, we were only reconstructing the front elevation meaning throughout the project we had to ensure the rest of the building remained structurally sound using temporary structural support. Client: Brightlingsea Association of Masonic Lodges Architect: TMA Chartered Surveyors- Property Consultants Contract Details: Value: £75,000 Duration: 16 Weeks Completed: September 20