M5 Junction 4 Phase 2 Widening, Bromsgrove
Case Study: M5 Junction 4 Phase 2 Widening, Bromsgrove www.van-elle.co.uk 01773 580580 info@van-elle.co.uk The £11m project was programmed to be delivered in 16 weeks as part of the Highways Agency ’s pinch point improvement programme and involved widening the existing 3 lane roundabout to 4 lanes. To deliver the project in such a constrained delivery period re- quired detailed planning and extensive liaison between Van Elle and principal contractor Carillion. In addition to the planned day shifts a number of night shifts and extended weekend working was planned when additional lane closures could be carried out. Van Elle were appointed to undertake all piling works for the pro- ject although the initial site work was to install 2 preliminary test piles to prove Van