Case Study
Longcliffe Quarry
Customer: Longcliffe Quarries Ltd. DNO: Western Power Distribution Location: Matlock, Derbyshire, UK WPD RMU GRP This connection was for newly installed 2 x 2 MW turbines within the Longcliffe Quarries property line. During the design, special provisions have been made for the customer HV substation where generation power was first diverted to the customer distribution boards for the quarry needs and then expor