Case Study
Quarry
Case Study Power Factor Correction Cauldon Low Quarry Annual Savings Achieved ? £9,391.43 ? 54.41 Tons Co2 ? 32,188 kW/h site ? 101,311 kW/h inc transmission Payback ? 11 Months Benefits ? Removal of Reactive Power Charges ? Reduction of 235 Amps per phase ? Reduction of 169 kVa Demand ? Improved utility The Quarry at Cauldon Low in Buxton is operated and owned by the Tarmac group of companies and is res