Case Study
Lime Street Development, Liverpool
Case Study Lime Street Development, Liverpool Project Name: Lime Street Development, Liverpool Client: ISG Construction Commenced: Phase 1 – December 2016 Phase 2 – August 2016 Duration: Phase 1 – 20 Weeks Phase 2 – 20 Weeks Project The project consists of new retail units to ground floor, a 3 storey 101 room Premier Inn on the front of the development and a 10storey 412 room student accommodation blocks to the rear. Scope The scope of work is broken down into the following elements: - • External perimeter retaining walls. • Ground floor slabs. • Internal drainage including outfall connection in Lime Street. • Incoming water trenches to retail units. • Internal ducting. • RC Foundations and holding down bolts. • Reduced level dig.