Case Study
Leveling the Ground at Babson’s Innovation Center
case study Leveling the Ground at Babson’s Innovation Center Project Overview Babson College required modification to their classrooms in Olin Hall. Black Bear Coatings and Concrete was brought in to integrate existing concrete slab with new concrete floors that would complete the re-envisioned room. The Process STEP 1: Shot blast/grind substrate flooring STEP 2: Apply Vapor Mitigation Primer STEP 3: CMP Specialty Product and CMP Diamond Cap applied STEP 4: Polished topping installed at a 1/4 inch (leveling floor) Project Details Project Name – Babson College, Olin Hall Type of Business – Non-Profit / Education Location – Wellesley, Massachusetts Size/Square Footage –2,100 sqft space Timeframe – 4 days (night work) Products – CMP Specialty Product, CMP Diamond Cap, Vapor Mitiga