Leighton Buzzard Station AFA
Leighton Buzzard Station AFA Leighton Buzzard station LEIGHTON BUZZARD VALUE £200K JUNE 2014 - OCTOBER 2014 FOUNDATIONS MAIN STEEL SPS WIRE RE-PROFILING REGISTRATION “AFA – improving access for all at stations across Bedfordshire” RAILWAY ELECTRIFICATION RAILWAY ELECTRIFICATION A s part of the AFA (Access for All) modifications at Leighton Buzzard Station, a new walkway bridge over the West Coast Main Line was installed across four tracks to provide access to all platforms. To facilitate these works, Pod-Trak were subcontracted to design, supply and install new foundations, structures, SPS, headspans, wire splicing and re-profiling of the OLE through the bridge. All works were carried out during possession/ isolation periods and necessary arrangements were