I-95 Section CP-2

I-95 Section CP-2

Pages 1 Pages

• Designed with foamed glass aggregate as lightweight fill over utility • PennDOT required an 18-foot-high embankment over a 100-year-old brick sewer • Philadelphia Water Department wanted no additional load on historic sewer • Contractor was able to install throughout December even during snow storm • A 3-foot cut of existing soil enabled an 18-foot-high embankment of foamed glass aggregate without additional surcharge • Embankment built to a 1:1 slope allowing access along slope and eliminating the need for an MSE wall The information contained herein is believed to be accurate and reliable. AeroAggregates, LLC accepts no responsibility for the results obtained through application of this product. AeroAggregates reserves the right to update information without notice.