Case Study

Hohe See and Albatros wind farms

Hohe See and Albatros wind farms

Hohe See and Alba- tros wind farms are located 95-100 km north of Borkum, Germany Location Germany Denmark 20 September 2019, Brave Tern and Blue Tern successfully finished the transport and installation at the Hohe See and Albatros wind farms where they had worked in tandem installing all 87 Siemens Gamesa SWT-7.0-154 turbines. Hohe See and Albatros wind farms are located in the German part of the North Sea and this was the largest offshore wind farm project under construction in Germany. The wind farms will provide up to 710,000 households with clean energy. Fact Hohe See consists of 71 turbines and the adjacent Albatros of 16 turbines 87 SWT-7.0-154 turbines installed with a total output of 609MW 5 April Brave Tern began in- stallation on Hohe See 20 September Final

Join for free to read