Hess Equatorial Guinea Sendje Ceiba FPSO – Phase 1 and 2

Hess Equatorial Guinea Sendje Ceiba FPSO – Phase 1 and 2

Pages 2 Pages

Case Study: Hess Equatorial Guinea Sendje Ceiba FPSO – Phase 1 and 2 Location: Offshore, Equatorial Guinea Following an unsuccessful attempt by another contractor to remove 200 tonnes of Oil Based Mud waste using high volume pump technology, Sureclean were approached by the client to devise an efficient and effective safe system of work, utilising the latest pumping technology. Following this approach, Sureclean carried out extensive trails, witnessed by the client whilst replicating the conveying of materials up to 100m horizontally and 60m vertically utilising hydraulically driven screw pumps. On successful completion of these trials, we were subsequently awarded the contract to undertake these works. Sureclean Scope Primary scope of work was to provide the necessary manpower and equipme