Case Study
Harsco
CASE STUDY Ref: 6565D NAME Metal Recovery & Ferrocut YEAR 2016 VALUE £101,000 CLIENT Harsco DURATION 3 Weeks Thompsons were appointed by Harsco as Principal Contractors to undertake selected demolition and dismantling at their Lackenby site in Redcar. There were two main work faces, comprising the Metal Re- covery Plant and the Ferro-cut Plant. Prior to commencement of works a full asbestos dem- oliti on survey was completed, to iden