Gymnasium & Field House Renovations

Gymnasium & Field House Renovations

Pages 2 Pages

Mt. Vernon High School Mt. Vernon, WA This project consisted of a major retrot of the existing facility located on the high school campus. The existing facility was approximately 58,500 square feet and included gymnasiums, locker rooms, restrooms, oces, concessions, weight training and aerobic rooms. The facility upgrade included modications to the plumbing, heating and ventilation, hydronic systems, the addition of restroom facilities, a classroom, an oce and a new entry. A re sprinkler system was added to the facility as well as the integration of the DDC system from the main campus. The Challenge: At the beginning of the project, we coordinated with the project architect to set a schedule for each of the projects phases. Adhering to the schedule was critical, since the school allo