Case Study

Gospel Oak To Barking Rail Bridges

Gospel Oak To Barking Rail Bridges

The project involved the replacement of four bridges on the Gospel Oak to Barking railway line over three weekends, during 50hr possessions of the railway. The project is part of a wider scheme by Network Rail to ensure railway infrastructure is upgraded to suit current traffic loadin

Join for free to read