Case Study

Gatwick Airport Ltd

Gatwick Airport Ltd

Pages 2 Pages

Client Gatwick Airport Ltd Value £0.4m Contract NEC3 Enabling works package for the Gatwick Stream Flood Attenuation project, which consisted of supervising over 30 archaeologists for over 6 weeks whilst they cleared the area for the subsequent project. Further works were instructed during the course of the project which included 240m of ducting for a UKPN HV cable diversion and construction of a haul road an