NUDURA Project Profile 866-468-6299 www.nudura.com FAST FACTS First Baptist Church - Marble Falls, T exas • The design of this structure consisted of the installation of metal structure within the ICF envelope • The ICF was incorporated throughout the entire building envelope, including the gables and contributing greatly to the overall energy performance of the church • The sound protection provided by the ICF was notably apparent during the Summer Boat Races that occurred, although they are heard from miles they were unheard from inside the church due to soundproofing walls. PROJECT STATISTICS Location: Marble Falls, T exas Type: Heavy Commercial Size: 65,000 sq ft. ICF Use: 43,000 sq ft. Cost: $10,000,000 Total Construction: 450 Days ICF Installation Time: 120 Days CONST