Case Study
EL6040 Floating Cover for Glycol Recovery Pond
EL6040 Floating Cover for Glycol Recovery Pond LOCATION: Lansing, Michigan TIMEFRAME: 30 Days NTP/ Finish SCOPE OF WORK: Design/Pre- con/Drawings/Submittals/Purchasing/Fabrication/Shipping/Installation/QC PROJE 36,000 SF Glycol Recovery Pond EL 6040 Floating Cover PROJECT PARTNERS: Capital Regional Airport Authority Challenge The owner asked for us to supply a replacement cover for a Modular Insulated Cover system (installed by others) that had failed, and was in need of emergency replacement with the following stipulations; 1) The new cover could not be of the same type, 2) The new cover must be resistant to ethylene glycol, 3) The new cover must be of a proven design, and 4) The new cover must be installed within 30 days of the contract being signed.The previous cover was a modular cov