Efficient Removal Technique Implemented for Feedwater Heater Replacements
Efficient Removal Technique Implemented for Feedwater Heater Replacements Day & Zimmermann Day & Zimmermann provided supervision and craft to remove and replace two feedwater heaters (FWHs) during a planned outage. The FWHs were stacked on two floors and surrounded by a structure, making them inaccessible to the overhead crane. Working with a specialty rigging company to access the units and maneuver the vessel, the team slid the units forward, jacked them up, and rolled them out on powered saddle rollers to a position where they could be accessed by the crane. The next-best removal technique would have added three weeks to the project. The upper unit was slid out, suspended, and lowered through a hole in the floor to follow the path of the lower unit. The upper unit was lowered with