Case Study

EF Education Center

EF Education Center

EF Education Center Program Summary • Designated “Energy Project of the Year” by the Association of Energy Engineers • Annual Electricity Savings: Electricity - 2,900,000 kWh / $464,000 Gas - 63,000 Therms / $82,000 • Total Installed Cost: $2,070,000 • Final EF Cost: $1,470,000 • NSTAR Incentives: $600,000 • Total Cost Reduction: $546,000 • Simple Payback: 2.7 Years Energy Efficiency Measures • Lighting • Controls • HVAC COMPREHENSIVE ENERGY EFFICIENCY TREATMENT EF Education First, a company that provides educational travel and cultural exchange programs throughout the world, was experiencing unmanageable energy costs at its 200,000 sq. ft. headquarters building in Cambridge MA. EF was also having difficulty maintaining thermal comfort levels in the relatively new buildi