Case Study
Easlea Road - Steel Framed Industrial Warehouse
Introduction This project involved the design and construction of a steel framed industrial Warehouse and Offices In addition, associated car parking and external works were also included in the works. Initiatives & Social Value It was important to the client that we stayed on programme, so we installed a ring beam to allow us to progress quicker and meant we could meet the programme, which was considerably tight. easlea road steel framed industrial warehouse Overall, very happy with the work Ashe has carried out and would work with Ashe again on future schemes. The building was completed in the expected time frame. Harry De Ferry Foster Savilles Investment Management Easlea Road, Bury St Edmunds, IP32 7BX Duration 33 weeks Start 06.03.17 Finish 26.10.17 Value £4