Dolwin3 -Transport & Float Over Installation Of The Dolwin Gamma HVDC Topside
A A Design FEATURES Client Nordic Yards GmbH, GE GmbH and TenneT Offshore GmbH Location Warnemunde, Dolwin field offshore - German Bight (North Sea), Eemshaven, Rotterdam, Papendrecht Period January 2015 – August 2017 Contractor Dockwise Shipping b.v. Seabed preparation March – April 2016 Fender Installation April 2017 Pile Cutting Campaign May 2017 Barge float over preparation Warnemuende May 2017 Transport of HVDC topside by wettow June 2017 Float over installation July 2017 Fender Removal campaign July 2017 BOSKALIS Royal Boskalis Westminster N.V. is a leading global services provider operating in the dredging, maritime infrastructure and maritime services sectors. The company provides creative and inno- vative all-round solutions to infrastructural chal- lenges in the