Case Study
Disston Avenue, Drainage Improvement Orlando, Florida
The 3 systems are installed underground, down the middle of Disston Avenue, a heavily traveled residential street in Orlando. Installation of the entire system took 60 days. Trench boxes were used to support the sides of the excavation while the precast concrete baf? e boxes and Storm Capture modules were installed using an excavator. Each of the 3 systems had to be installed individually with the roadway re-opened to local traf? c between c