Data Hall 2, Abbey Wood www.integral.co.uk DefenceCase Study Data Hall 2, Abbey Wood Integral Building Services completed a Data Centre for the MOD as Principal Contractor on a design and build project, delivering all Mechanical and Electrical Services and associated Builderswork. Completion of Data hall 2 was the latest in a line of completions in new data centre build provision. As centres of national security these state of the art designs have been supplied to exacting standards in terms of security, resilience and carbon footprint, achieving a PEU of 1.2. DH1, a 128 rack Data Hall supplied by Integral Building Services a year previously demonstrated an exceptional efficient design and operation , the contract for DC2 doubled the size of the complex by a further 132 racks.