Case Study
Csa Lateral Development
PROJECT FACT SHEET SCOPE • Mine development and ground support including load & haul of development waste to stope fill areas. • Loading of development ore into client trucks as required. • Intensive ground support regimes (up to 4 passes) CSA Lateral Development, Cobar, NSW Project Value: $113M l Project Term: 36 months l Employees: 84 PROJECT STATISTICS • Targeting 400m/month development CONTRACT TYPE •