Case Study
Costerfield Development Project
PROJECT FACT SHEET SCOPE • Independent development of the 4800 decline including drilling and blasting, load and haul, installation of ground support and mine services • Requirement that all underground equipment must access through a 2.7m maximum height Costerfield, Central Victoria Project Value: $4.0M l Project Term: 6.5 months l Employees: 27 PROJECT STATISTICS • 1220m of development • 80,000 tonnes of waste