Costain, VINCI, Bachy JV Industrializes Delivery of UK’s Largest Water Infrastructure Project

Costain, VINCI, Bachy JV Industrializes Delivery of UK’s Largest Water Infrastructure Project

Pages 2 Pages

Leveraging SYNCHRO TM 4D Saves 90 Days During Two Years of Construction Fast Facts • CVB JV established a connected data environment and implemented 4D construction modeling for the GBP 850 million Thames Tideway East Tunnel. • SYNCHRO 4D helped create more than 30 digital 4D construction models at five sites, streamlining construction planning activities and improving progress tracking and management. • The team facilitated 4D collaborative planning to optimize on-site construction works. ROI • Using 4D modeling reduced the overall construction program by over 90 days over two years, saving GBP 1 million.